Zhengzhou Zhenggang San Road-Longzhong Road
Project Place:Zhengzhou
Construction company:China Railway Engineering Corporation
Project Name:Zhengzhou Zhenggang San Road-Longzhong Road
Height of the Structure:6.5m
Key points:The thickness of the precast slab is 1.3m. As time is limit, under the premise of safety, speed up the construction to make sure the project finish on time.



![]()